Ayakoromo Bridge: Delta Govt Hails Progress, Targets 2027 Completion

Share this:

ASABA, NIGERIA — The Delta State Government has expressed satisfaction with the pace and quality of work on the Ayakoromo Bridge across the River Forcados.

The government urged construction giant Setraco to sustain its efforts and ensure the project is completed within the scheduled timeline of December 2027.

The Commissioner for Works (Highways and Urban Roads), Comrade Reuben Izeze, gave the commendation on Thursday. He spoke during an inspection of the project alongside engineers from the ministry.

Progress and Challenges

Izeze acknowledged the challenges posed by the difficult terrain and weather conditions. But he said the contractor had made appreciable progress.

He added that the ministry’s engineers had confirmed that work was proceeding in line with the approved schedule.

READ ALSO:  2027: ADC Knocks PDP Over Moves to Woo Obi

“Setraco has done appreciably well, considering the weather and the terrain. However, there is still room for improvement. Our engineers have confirmed that work is progressing according to schedule, and the quality of engineering is encouraging,” he said.

The commissioner urged the contractor to intensify its efforts. He said the residents of Egbo-Ide in Ughelli South Local Government Area and Ayakoromo in Burutu Local Government Area should benefit from the project as soon as possible.

He also commended engineers of the Ministry of Works for maintaining effective supervision throughout his temporary absence. He stressed the need for continued monitoring to ensure that construction standards and delivery timelines were not compromised.

READ ALSO:  What does Brexit mean for Africa? – BBC

“We hope Setraco will maintain the standards it is known for, keep to the agreed timeline and deliver a quality project that will serve the people,” Izeze said.

Contractor’s Assurance

Speaking during the inspection, Setraco’s Project Manager, Nabil Chahiene, expressed confidence that the bridge would be completed in December 2027.

“By His grace, the project will be completed in 2027,” he said.

Project Details

The Ayakoromo Bridge was awarded on December 16, 2022, at a contract sum of more than ₦39 billion.

The bridge is expected to provide a vital link between Egbo-Ide and Ayakoromo communities. It will improve the movement of people and goods across the River Forcados.

Upon completion, the bridge is expected to ease transportation difficulties and strengthen economic activities. It will also improve access to essential services for residents of the two communities and neighbouring areas.

READ ALSO:  NJC Begins Emergency Meeting Over Onnoghen, acting CJN to abstain

What This Means

The bridge is a critical infrastructure project for Delta State. It will connect communities that have long been separated by the river.

The project will boost economic activity in the region. It will also improve the quality of life for residents.

What Happens Next

Setraco will continue construction work. The government will monitor progress to ensure timely delivery.

For now, the focus is on completing the project by December 2027. Residents are hopeful that the bridge will transform their communities.