The Federal Government is seeking an additional $500m loan from the World Bank to expand electricity access through renewable energy, which would raise the bank’s total financing for Nigeria’s Distributed Access through Renewable Energy Scale-up project to $1.25bn.
The proposed facility will increase the existing $750m financing for the project, known as DARES, which is being implemented by the Rural Electrification Agency.
According to a World Bank Project Information Document obtained by The PUNCH on Sunday, the additional financing is scheduled for consideration by the bank’s Board of Executive Directors on December 18, 2026.
The document, prepared on November 13, 2026, explained that the funding would support the expansion of electricity services to households, businesses, schools, healthcare facilities and underserved communities through mini-grids and standalone solar systems.
It stated that the additional financing would accelerate the deployment of renewable energy infrastructure, particularly in communities without access to the national electricity grid.
“The proposed AF will enable the scale-up and expansion of electricity services through mini grids and standalone solar systems, while sustaining the momentum of private sector-led access delivery,” the document stated.
The proposed borrowing comes as Nigeria continues to face electricity supply challenges, with many households and businesses relying on petrol and diesel generators to cope with frequent outages.
The World Bank estimated that 87.2 million Nigerians lacked access to electricity in 2024, despite an improvement in the national electrification rate from 52.5 per cent in 2015 to 61.2 per cent in 2024.
Rural communities remain particularly underserved, with only 32.9 per cent of residents having access to electricity. This leaves more than two-thirds of the rural population without power.
The bank said the existing DARES financing was designed to provide electricity connections to more than 18.8 million people, representing about 22 per cent of Nigeria’s electricity access deficit.
It estimated that the country would need approximately $23bn to achieve universal electricity access by 2030.
Distributed renewable energy solutions could provide electricity to more than 60 million people at a lower cost than conventional alternatives.
Project cost rises to $2.94bn
The proposed additional financing would also increase the overall cost of the DARES project from $2.06bn to $2.94bn, representing an increase of $880.2m, or 42.71 per cent.
Of the additional amount, the World Bank is expected to provide $500m, while the French Development Agency would contribute $116.2m. Another $264m is expected from commercial financing.
Total commercial financing under the programme is projected to rise from $1.028bn to $1.292bn.
The wider financing package also includes $193.8m from the Japan International Cooperation Agency, $49.1m in trust fund resources contributed through a United States Department of Justice-supported fund, and $40m from other development partners.
Under the proposed arrangement, the World Bank’s $600m shorter-maturity loan component would remain unchanged, while its IDA credit component would increase from $150m to $650m.
The additional $500m would therefore bring the bank’s total commitment to $1.25bn, subject to approval by its board.
Only 17.13% of original financing disbursed
Meanwhile, an analysis of the World Bank’s transaction records for the existing project showed that $128.44m had been disbursed from the original $750m commitment as of October 22, 2026.
This represents approximately 17.13 per cent of the approved financing, leaving about $621.56m, or 82.87 per cent, yet to be recorded as disbursed in the transaction data reviewed.
The original financing was structured into three commitments of $350m, $250m and $150m, all approved on December 14, 2023.
The relatively low recorded disbursement comes as the Federal Government seeks additional funding to expand the programme.
However, the World Bank explained that access to some of the funds depended on meeting performance conditions, including regulatory reforms and institutional improvements.
The document stated that $300m had been unlocked after the government fulfilled two performance-based conditions.
The original DARES financing was approved on December 14, 2023, and became effective on November 15, 2024. Its objective is to expand electricity access through privately led distributed renewable energy projects.
The World Bank’s Country Director for Nigeria, Taimur Samad, endorsed the latest project document on November 13, 2026, while the appraisal date was listed as October 23, 2026.